General contractor
General contractor
– installation of the Cooling tower of the extraction shop
– installation of the cooling tower of the refinery shop
– installation of the cooling tower of the barometric system of the refinery shop
– installation of pumping stations, HVO
– installation of technological pipelines
– installation of a transformer substation
09.2020 Start of the project
04.2021 Completion of the project